Last week we built the foundations for the sauna building.
A wheel loader moving the fine gravel for the bottom earth filling and crushed rock/ballast which prevent capillary rise of the water from the soil to the base of the building. The building site is hillside so the lorry driver couldn't dump the earth filling there because there's no road going there.
Then we laid out 25 cubic meters of fine gravel with shovels..

An excavator would've been nice but the guy who brought the wheel loader had his excavators working on a larger site and we had to get the job done at that day.. Well it wasn't too much when there are enough people.
Examining the underdrain piping.
All ground layers had to be ran with a soil compactor.
Me examining the results.
And me again making the iron reinforcements for the base concrete.
The masonry of the light weight concrete blocks.
Ready pillars.
Final top soil filling with fine gravel, again with shovels..
Parging the pillars.
Now only the building it self needs to be finished.

Well it's an easier job than making the foundations because it's a full packet building so all the timber is ready cut in correct length etc... It's a bit like a assembling a large lego-structure.
Also an excavator is needed to do the final landscaping around the building.. It's a bit coarse currently.